Projects
A five-year capex envelope you can read at a glance.
Expansion, electrification and shore-power programmes across the group, with milestones on a single year-axis. Each card links to the terminal it touches; budget envelopes are quoted in millions of US dollars.
- In progress
Harbor Point berth extension
Extending the quay at Harbor Point by 400 metres to accept two additional 24,000-TEU vessels alongside.
2024 Environmental impact assessment2025 Quay wall piling starts2026 First two cranes commissioned2027 Operational - In progress
Coastal Reach electrification
Replacing the remaining diesel yard tractors at Coastal Reach with battery-electric units and a 6 MW charging hub.
2023 Pilot fleet of 12 electric tractors2024 Charging hub commissioned2025 Fleet conversion 70% complete2026 Full electric operation - In progress
Crosscurrent Strait shore power
Cold-ironing on berths M1 and M6 at Crosscurrent Strait, with a grid upgrade to support the additional load.
2024 Grid capacity study2025 Substation build2026 First vessel cold-irons - Completed
Silverbay dry-bulk conveyor loop
A fully enclosed conveyor loop at Silverbay that removes open-air stockpile handling and cuts dust emissions by 38%.
2022 Foundation works2023 Conveyor installation2024 Operational - Planned
Northbank ro-ro expansion
Two additional ro-ro berths at Northbank to support the projected growth in vehicle and project-cargo volumes.
2025 Design and permitting2026 Construction starts2028 Operational