Projects

A five-year capex envelope you can read at a glance.

Expansion, electrification and shore-power programmes across the group, with milestones on a single year-axis. Each card links to the terminal it touches; budget envelopes are quoted in millions of US dollars.

2022202320242025202620272028
  • In progress

    Harbor Point berth extension

    Extending the quay at Harbor Point by 400 metres to accept two additional 24,000-TEU vessels alongside.

    Budget
    410 M USD
    Target completion
    2027
    2024 Environmental impact assessment
    2025 Quay wall piling starts
    2026 First two cranes commissioned
    2027 Operational
  • In progress

    Coastal Reach electrification

    Replacing the remaining diesel yard tractors at Coastal Reach with battery-electric units and a 6 MW charging hub.

    Budget
    88 M USD
    Target completion
    2026
    2023 Pilot fleet of 12 electric tractors
    2024 Charging hub commissioned
    2025 Fleet conversion 70% complete
    2026 Full electric operation
  • In progress

    Crosscurrent Strait shore power

    Cold-ironing on berths M1 and M6 at Crosscurrent Strait, with a grid upgrade to support the additional load.

    Budget
    62 M USD
    Target completion
    2026
    2024 Grid capacity study
    2025 Substation build
    2026 First vessel cold-irons
  • Completed

    Silverbay dry-bulk conveyor loop

    A fully enclosed conveyor loop at Silverbay that removes open-air stockpile handling and cuts dust emissions by 38%.

    Budget
    54 M USD
    Target completion
    2024
    2022 Foundation works
    2023 Conveyor installation
    2024 Operational
  • Planned

    Northbank ro-ro expansion

    Two additional ro-ro berths at Northbank to support the projected growth in vehicle and project-cargo volumes.

    Budget
    220 M USD
    Target completion
    2028
    2025 Design and permitting
    2026 Construction starts
    2028 Operational